Q12- Docking Plan and Paint Scheme contents.

Answer

The docking plan contents are
1. The overview of the bottom of the ship
2. It gives us the location of the anodes
3. It is the location of the openings and such as the overboard valves
4. And give us the location of the sea chest along with the greetings
5. It give us the location of the eco sounder speed log draft cages etc
6. It gives us the location of the dream plugs of the various double bottom tanks . Forbid ships each double bottom tank will have two plugs were for small ships on it will only have one plug
7. There are two talking plans so that one will be used during one Dry doc and then other will be used during the other Dry doc
8. The hull is damaged under ship is going for Dry doc in internal water inspection should be carried out so that a new alternate docking plan will be prepared and then docking will happen according to that

The contents of the paint scheme are
1. The trade name of the paint
2. The method of application that is my brush or by spray or by roller 3. The curing time of the paint
4. The drying time of the paint
5. The thickness of the paint layer
6. The number of courts to be applied
7. The storing requirements of the paint

Paint thickness-

Wet film thickness check- Comb gauge.
Dry thickness check – Elcometer.