How will u remove propeller shaft

Answer

Propeller shaft / tailshaft removal procedure
  1. Preparation
    • Vessel to be in dry dock and properly supported on blocks.
    • Obtain company approval and inform Class/Surveyor as shaft withdrawal is part of a statutory/class survey or repair.
    • Prepare risk assessment, toolbox talk, lifting plan and permits.
    • Study shafting drawing, coupling arrangement, bearing positions, shaft weight and centre of gravity.
    • Arrange suitable chain blocks/jacks, shaft trolley/rollers, hydraulic equipment and lifting points.
  2. Before dismantling
    • Take and record:
      • tailshaft bearing clearances,
      • shaft wear-down readings,
      • propeller position/reference marks,
      • coupling alignment/reference marks.
    • Check shaft alignment condition before disturbing the system, where required.
  3. Remove propeller
    • Remove rope guard and propeller cone/cap.
    • Remove locking arrangement and propeller nut.
    • For a keyed or keyless propeller, use the approved hydraulic/oil injection arrangement or propeller withdrawal gear.
    • Support the propeller by crane/chain blocks before releasing it.
    • Withdraw and land the propeller safely.
    • CPP arrangement additionally requires disconnection of hydraulic/control connections as per maker's procedure.
  4. Disconnect shafting inside engine room
    • Open intermediate shaft/tailshaft coupling bolts or flange connection.
    • Match-mark coupling components before dismantling.
    • Support the shaft adequately so that no load is transferred abnormally to bearings or stern tube.
  5. Remove stern tube sealing arrangements
    • Drain stern tube lubricating oil as necessary.
    • Disconnect oil pipes, header tank connections and monitoring lines.
    • Remove aft seal housing/components as required.
    • Remove forward seal/gland components if they obstruct shaft withdrawal.
    • Protect seal liners and machined surfaces.
  6. Withdraw the tailshaft
    • Fit shaft trolley/rollers and suitable supporting arrangements.
    • Carefully move the shaft aftwards, normally through the stern tube.
    • Continuously support the shaft while withdrawing so that:
      • stern tube bearings are not damaged,
      • shaft journals do not strike the bearing,
      • seal liners and shaft surfaces are protected.
    • Use crane support at the aft end as the shaft emerges.
    • Land the shaft on properly prepared wooden/rubber-lined supports.
After withdrawal — important examination points

Clean the shaft and carry out: