MEO CLASS 1 · ORAL QUESTION 27

Q11- Bunkering Preparation and Procedure. Precautions, instructions to Juniors?

Answer

Ans: Preparation before bunker operation. Refer to Bunkering Procedure and bunkering Checklist as per SMS.

1.The chief engineer should calculate and check which bunker oil tanks are to be filled after he receives

confirmation from the shore office about the amount of fuel to be accepted. RA to be made.

2.It might be required to empty some tanks and transfer the oil from one tank to other. This is required to prevent the mixing of two oils and prevent incompatibility between the previous oil and the new oil. 3.The sounding of other fuel storage tank (not be used in bunkering operation) should also be taken to keep a record of fuel already present onboard. This will help the ship’s officer in case any valve is leaking, and the bunker oil is being transferred to the unwanted tank.

4.A meeting should be held between the members that will take part in the bunkering process, and they should be explained about the following:-

a) Which tanks are to be filled
b) Sequence order of tanks to be filled
c) How much bunker oil is to be taken
d)Bunkering safety procedures
e)Emergency procedures to be follow in case of spill occurs. f) Responsibilities of each officer are explained.

5. Sounding is taken before bunkering and record is made
6. A checklist is to be filled so that nothing is missed
7. All Deck scuppers and save all trays are plugged
8. An overflow tank is provided in the engine room which is connected to the bunker tank and bunker line. Ensure the overflow tank is kept empty to transfer excess fuel from the bunker tanks
9. Adequate lighting at the bunker and sounding position are to be provided
10. No smoking notice should be positioned near the bunkering station.

Onboard communication, signs, and signals to stop the operation between the people involved in bunkering are to be understood by all the crew involved in the operation.

12. Red flag/light is presented on the masthead
13. Opposite side bunker manifold valves are closed and appropriately blanked
14. Vessel draught and trim is recorded before bunkering
15. All equipment in SOPEP(shipboard oil pollution emergency plan) locker are checked and kept near the bunkering station
16. When bunker ship or barge is secured to the ship side, the person in charge on the barge is also explained about the bunker plan
17. Bunker supplier’s paperwork is checked for the oil’s grade and the density if they are as per the specification 18. The pumping rate of the bunker fuel is agreed with the bunker barge/ bunker truck
19. The hose is then connected to the manifold. The condition of the hose must be checked properly by the ship staff and if it is not satisfactory, same to be notified to the chief engineer
20. Most of the bunker supplier send there crew to connect the bunker oil pipeline coming from bunker ship/ barge. The ship staff must recheck the flange connection to eliminate the doubt of any leakage.

21. Once the connection is made, the chief engineer will ensure all the line valves which will lead the bunker fuel to the selected bunker tanks are open, keeping the main manifold valve shut
22. Proper communication between the barge and the ship is to be established
Sign and signals are to be followed as discussed in case of communication during an emergency
24. Most bunkering facilities (ship/ barge/ terminal/ truck etc.) provide an emergency stop switch which controls the bunkering supply pump. Ensure to check its working before commencing the operation
25. Once all the checks are done, the manifold valve is open for bunkering.

During bunkering operation:
1.During the start of the bunker, the pumping rate is kept low; this is done to check that the oil is coming to the tank to which the valve is opened
2. The ship staff (4/E) must track the sounding of selected bunkering tank and other tanks which are not involved in the operation to ensure oil is only going to the selected tank.

3. After confirming the oil is coming to the proper tank, the pumping rate is increased as agreed before
4. Generally, only one tank filling is preferred because gauging of more than one tank at a time increases the chances of overflow
The max allowable to which tank is filled is 90 %, and when the tank level reaches about to maximum level, the barge is told to pump at low pumping rate to top up the tank, and then the valve of other tank is opened 6. During bunkering, sounding is taken regularly and the frequency of sounding is more when the tank is near to full. Many vessels have tank gauges which show tank level in the control room, but this is only to be relied upon if the system is working correctly.

9. The temperature of the bunker oil is also to be checked; generally, the barge or supplier will provide the bunker temperature. Temperature is a Critical parameter, especially for bunker fuel such as heavy fuel oil, and any Deviation in the provided temperature value may lead to a shortfall in bunker supply
8. A continuous sample is taken during bunkering with the help of sampling cock at the manifold. Bunker sample is a full representative sample.

After bunkering:

1.Ensure all sounding pipe caps are closed and keep a watch on those storage tank vents during air blow of bunker lines.

2.Take sounding of all tanks after completion of bunker and do final calculation include trim, heel and temp correction.

3.Four samples are taken during bunkering. One is kept onboard, one for the bunker ship or barge, one for analysis, one for port state or IMO
4.The chief engineer will sign the bunker receipt (BDA/) and the amount of bunker received
5.If there is any shortfall of bunker received the chief engineer can issue a letter of protest against the barge/supplier (in case the deficit is not agreed by the bunker supplier).

Instruction to juniors:

1.ER should be manned during bunkering operation.

2.Follow all instruction as discussed in Pre-bunker meeting or bunker check list. 3.Bunker manifold always be manned and with proper communication at all time. 4.Always wear proper ppe.

5.In case of any doubt, consult CE.

6.In case of any leakage , stop the bunkers first and then investig ate.