MEO CLASS 1 · ORAL QUESTION 42

MLC implementation on new ship

Answer

The implementation of the Maritime Labour Convention (MLC, 2006) on a newly constructed ship is a statutory process involving the Shipbuilder, Shipowner/Manager, Recognized Organization (RO/Class), and Flag State Administration (such as DG Shipping / MMD in India).

Because MLC covers both structural design (Title 3) and operational compliance (Titles 1, 2, 4, and 5), implementation begins at the drawing board long before the ship is delivered.

Overview of Implementation Phases

Phase 1: Structural & Design Approval (Yard Construction Stage)

During the vessel's design phase, detailed drawings of the accommodation and galley spaces must be submitted to the Flag Administration or Recognized Organization (RO) for statutory plan approval under MLC Title 3 (Accommodation, Food & Catering).

Key Structural Requirements Inspected

Parameter

MLC Title 3 Statutory Requirement

Headroom

Minimum 203 cm clearance in all accommodation spaces where seafarers stand or walk.

Cabin Dimensions

Single cabins for officers; individual berths with minimum inner dimensions of 198 cm × 80 cm. Minimum floor area varies by rank and ship tonnage.

HVAC & Insulation

Adequate heating, air conditioning, and ventilation systems designed for extreme climatic operational limits.

Sanitary Facilities

En-suite or nearby private head/shower facilities for all officer cabins; minimum ratios for ratings.

Hospital Accommodation

Mandatory on ships carrying ≥15 seafarers on voyages > 3 days. Must be used exclusively for medical purposes with dedicated head and shower.

Noise & Vibration

Full compliance with the IMO Code on Noise Levels on Board Ships (Resolution MSC.337(90)) to protect sleeping quarters and mess rooms.

Galley & Mess Rooms

Hygienic food preparation surfaces, stainless steel construction, adequate refrigeration, and mess room capacity sized for crew complement.

Phase 2: Documentation & Operational Preparation

Prior to ship delivery, the Shipowner/Management company must establish the administrative framework for onboard working and living conditions.

1. DMLC Part I and Part II Issuance

2. Seafarer Employment Agreements (SEAs) & Crewing

3. Financial Security Certificates

Posting mandatory certificates on board prior to departure from the shipyard:

4. Social Connectivity & Internet Provision (2022 Amendments)

Phase 3: Interim Inspection & Delivery Certification

Because a brand-new ship has no operational history (e.g., no past wage records or rest hour logs), it cannot be immediately issued a full 5-year certificate upon leaving the builder's yard.

The Interim Inspection

Issuance of Interim Certificate

Phase 4: Initial Full Audit & 5-Year Certification

Before the 6-month Interim Certificate expires (typically scheduled between Month 3 and Month 5 of trading), the vessel must undergo an Initial Full MLC Inspection.


Scope of the Full Audit

  1. Audit of Operational Records: The auditor inspects at least 3 months of operational evidence generated since delivery:
    • Signed monthly rest hour records (checking for STCW/MLC rest period breaches).
    • Wage account slips, allotment records, and evidence of timely monthly payment.
    • Food and potable water quality inspection logs, temperature records, and water analysis.
  2. Private Seafarer Interviews: The inspector conducts private, random interviews with crew members from various ranks (without officers present) to verify:
    • Fair treatment and absence of bullying/harassment.
    • Awareness of the Onboard Complaint Procedure.
    • Provision of adequate food, drinking water, and working gear/PPE.
  3. Issuance of Final Certificate:
    • Upon successful completion, the auditor endorses DMLC Part II and issues a full Maritime Labour Certificate, valid for up to 5 years.
    • Subject to an Intermediate Inspection between the 2nd and 3rd anniversary dates.