MEO CLASS 1 · ORAL QUESTION 13

Critical Operational Phases of Drydocking

Answer

The two most critical drydocking phases are taking the blocks during pumping down and leaving the blocks during refloating, because the ship’s support changes between buoyancy and the dock blocks and its effective stability continuously changes. As Chief Engineer, I will maintain the approved tank condition, prohibit unauthorised liquid transfer, ensure continuous communication, monitor list and leakage, and stop the operation immediately if any abnormality occurs.”

1. Taking the blocks and pumping down — most critical phase

When water is pumped out, the keel first contacts the keel blocks.

As the block reaction increases:

During this period:

The critical period continues from first keel-block contact until the vessel is firmly supported by the keel and side blocks. Dry-dock stability rules specifically consider conditions from initial touchdown through normal supported operation.

2. Refloating and leaving the blocks — second most critical phase

Refloating is the reverse of docking.

As water rises:

During refloating:

The vessel must be fully afloat and clear of the blocks before propulsion or thrusters are used.